Bored Piles Philippines |
|||||
Foundation Specialists,
Inc., Legaspi Towers 200, 107 Paseo De Roxas, Makati City 1226, Philippinws. Phone +63 2 8817
6826 e-mail address CLICK THIS |
|||||||||||||||||
Bored Piles by Foundation Specialists. Bored piles are cast in place cylindrical piles excavated either by use of rotary equipment operated augers , buckets,
under static drilling fluid or large drill bit (for hard rock) with reverse circulation, with chisel grab
and casing oscillator for bouldery ground, with large diameter DTH hammers and compressed air (drilled
piles), among others. Most common
large diameter bored piles, are installed through an overburden of cohesive or cohesionless soil strata, with or without water
table, down to firmer ground, to achieve the design bearing capacity by skin friction, base bearing or both, to serve as foundation
piles for residential, commercial, institutional buildings, industrial complexes or infrastructures. Bored piles installed in common soil with the presence
of water table, generally require the use of a short temporary steel casing and a drilling fluid as static suspension to provide
support to the surrounding soil while excavating the pile and until complete backfill of the pile excavation with concrete,
in order to prevent cave-in of the excavation and destabilizing the surrounding soil formation. The preparation and handling by most effective drilling fluid, Bentonite Mud,
is a sophisticated technology by itself and requires a complete set up of dedicated equipment and (basic)
field laboratory. The most common
diameters of bored piles range from 0.6 meter to 3.0 m meters, likewise length
can range from few meter to sixty or more meters, depending upon design loads and soil parameters. Bored piles can be heavily reinforced if required by design,
rebar cages usually are prefabricated in segments with length and weight depending upon available commercial lengths
of rebars and available lifting equipment. Splicing of rebar cages can be done by lap
splice, welded lap splice or mechanical threaded couplers. Casting is done by pouring concrete with the design strength and
slump as required, through watertight segmental Tremie Pipes, starting from the pile bottom and letting the tremie pipe bottom-end
remain at least 3 meters submerged in concrete until the completion of pouring, to guarantee the pile continuity and the final
good quality of the concrete cast. Drilling
fluids, if needed, can be water, a suspension of bentonite (bentonite mud), a suspension of polymers, depending
upon soil type, soil conditions, presence and elevation of water table, chemical properties of water table (Ph, Salinity). Steel casings can be temporary, in which case the wall
thickness is usually big enough to allow many uses, are provided with collars for easy handling by vibro hammers
and diameter slightly larger than bored piles’ nominal diameter, to allow easy passage of
drilling tools. Permanent casings, if needed, are sacrificial casings and as such the wall thickness is
as small as allowed by the need to drive the casing through the ground. Bored piles are commonly employed for bridge foundations, on land and water, because
the versatility of bored piles design and execution allows the construction of practically any needed
diameter, including the very large diameters, and the pile reinforcement can be provided as heavy as needed by seismic design
and the codes (it is not uncommon to have double wall rebar cages in order to accommodate all the needed bars, however care
shall be taken to leave sufficient space between bars for concrete to flow through). Bored piles are also used to form retaining walls (see PileWall), as contiguous
pile wall or secant pile wall or aligned pile wall, with or without post tensioned soil anchors as tie back . Bored piles testing is usually done in two (2) stages,
first stage testing to verify design assumptions and achievable design load , is done before starting the execution of the
working piles: test piles are installed in the proposed construction area, as per design, and tested, first for integrity
and continuity by P.I.T. (Pile Integrity Test) then for load bearing capacity , either by Static Load Test
or by Dynamic Load Test PDA, (Pile Dynamic Analysis). At times the Designer might require a Pull-out test and a lateral load
test. Once the design pile capacity
has been confirmed, Bored Piles construction for the working piles starts and quality
control is then done on representative piles. Quality Control consists of testing the material used for the bored piles, i.e.
reinforcing bars and concrete, then testing of the piles at random with PIT and PDA, and predetermined
piles with static pile load test. Predetermined piles can also be tested using the cross-hole ultrasonic test, by inserting
instruments through vertical pipes installed within the reinforcing steel cage all throughout the bored pile length. As Part of our Services WE OFFER Design and Construct of BORED PILES, DIAPHRAGM WALLS, SOIL IMPROVEMENT &, CONSOLIDATION by FS SOIL-CEMENT COLUMNS, JET-GROUT, STONE
COLUMNS / GRAVEL PIERS, WICK
DRAINS & SURCHARGE, HEAVY TAMPING, VIBRO-REPLACEMENT, GROUTING. CONTACT US BY e-mail <CLCK HERE> or CALL +63 2 8817 68 26 VISIT US at
<Legaspi Towers 200, 107 Paseo De Roxas Makati City, MetroManila, Philippines> Survey Works - Staking of Piles' Positions The first step to be taken, when starting a project involving the installation / execution
of Cast in Place Reinforced Concrete Bored Piles is to survey the working areas, establish fix reference points and proceed
to stake out the piles’ positions. EQUIPMENT: Depending upon the diameter and depth of the
Bored Piles and site conditions, the Contractor will mobilize the proper Bored Piling Rig(s), the support equipment and the
proper Boring Tools as needed. Temporary Casings (Or Permanent Casing if required) will be at site, as well as a Vibrohammer to drive the casings. The Bored Piles will
be excavated using crane mounted or self-propelled rotary drilling rig with telescopic Kelly bars, drilling bucket and auger
of proper diameter. If Boulders are expected to be found in the soil formation where Bored Piles have to be executed, Chisel
and Grab shall also be mobilized and kept ready at site. This equipment is selected for each project based on its capability
to execute bored piles of the required diameter and length, and in accordance with the dimensions of working areas.
Service Crane(s), Wheel Loader, Backhoe, Genset(s), Water Pumps, Welding Machines, Equipment, Plants and Tools for Reinforcing
Bar Cages Fabrication, and other Support Equipment and Tools will also be mobilized to site, as needed. TEMPFACIL: Containerized Office fully furnished and equipped, Containerized Field Warehouse, “Portalet(s)”
(Portable Toilets), a covered area foe equipment maintenance will be proved at site. INSTALLATION & RETRIEVAL OF TEMPORARY CASING: Temporary casings of proper diameter and thickness will be installed in the exact pile
position, to stabilize the hole. The rebar cage will hung from the top of temporary casing while additional segments
are being spliced, and eventually, during concrete pouring, in order to keep the Rebar cage centered and At the end of Pouring
the temporary casing is extracted. BORING THE PILE POSITIONS: The excavation of the piles will proceed using a drilling bucket and or
an auger as needed, depending on the quality and strength of the soil. If boulders are encountered, the same will be
broken and removed using chisel and grab. The excavation of the pile will proceed until the design depth is reached.
The excavated soil will be brought to the surface by the auger/bucket and will be loaded to dump trucks for proper disposal.
If Piles haveto be executed in the presence of Water Table, it is important to identify the exact elevation of it . so that
the head elevation of the drilling fluid employed will be kept sufficiently higher than that of the water table,
in order maintain inside the borehole a higher hydrostatic pressure than the one existing outside and thus helping to prevent
cave-in when excavating cohesionless soil. When executing Bored Piles using water of Polymer suspension as drilling
fluid , fine in suspension in the drilling fluid will precipitate to the bottom of the excavation in abour 30 minutes once
pile design depth has been reached and the drilling tools retrieved. Before installing the rebar cage, the bottom
of the pile will have to be properly cleaned up, by removing all the fines and debris by means of a “cleaning
bucket” with a sealable bottom. For Piles in unstable granular ground Static Bentonite Suspension, as drilling
fluid, is advisable. The handling of Bentonite Mud is a Technology in itself and must be mastered in order to take full
advantage of it. INSTALLATION OF REBAR
CAGES AND TREMIE PIPES: Once the pile
bottom is cleaned, the fabricated rebar cages will be installed, segment by segment, into the hole, well secured, in sequence,
to each other. After all the segments of the rebar cage are installed inside the bored hole, the whole
rebar cage will be suspended from the top of the steel temporary casing, with the bottom about 10 centimeters
higher than the bottom of excavation, in order to keep it straight and centered in the hole Next the tremie pipes
will be installed down to the pile excavation bottom. A feeding hopper will be installed at the top of the tremie pipe, and
a paper plug will be inserted inside the top tremie pipe to serve as the interface between the concrete being poured and the
drilling fluid filling the excavation, with the purpose of preventing dropping and washing the concrete. For very large pile
diameters, two tremie pipes are used for pouring each pile, in order to have an even raise of the concrete in the excavation,
while pouring. The Tremie Piles will be shortened gradually while the concrete is raising inside the excavation, care shall
be taken to maintain the tremie pipes’ bottom-end always submerged by about no less than 3 meters inside the raising
concrete, to avoid “cutting” the piles POURING CONCRETE INTO BORED PILES BY TREMIE PIPES: The concrete to be poured shal be self-levelling, made such by reducing water and obtaining the
8” slump by using super plasticizer additives Concrete will be conveyed to the pile by direct
pouring, with the transit mixer dumping concrete directly to the feeding hopper topping the tremie pipes. The pouring
of concrete will be done using high slump (7-8”) concrete to assure that the pile will eventually be filled up with
concrete, inside and outside the Reinforcing Bars Cage.. The concrete will be poured into the top hopper of the tremie pipe
and will be delivered to the bottom of the pile by the tremie pipes. The bottom of the tremie pipe will be left submerged
in concrete to prevent forming “dirty “ joints t. While pouring proceeds, the yield of the concrete inside
the pile will be measured after every transit mixer has completely discharged its load. 3-4meters of tremie pipe will be left
submerged in the concrete and the shortening of the tremie pipes will proceed by removing segment by segment of
tremie pipe from the top. If by design the pile head is at Ground Level, the pile will have to be over poured with concrete
overflowing the bore hole itself until all contained impurities or debris will have been flushed out and the pile will be
thus ready for the pile cap. ff overflowing the pile with concrete is not possible, the pile will be overpoured
by a volume of concrete sufficient to carry all so called “dirty Concrete above the Pile cut-off elevation. Temporary
casing is usually 2,5 to 3.0 meters long, in which case, at the end of pouring the tremie pipes will be removed ahead
of lifting off the casing, but if the temporary casing is a long one, the temporary casing will be removed while leaving
the tremie pipe secured in place and with its bottom 3 to 4 meters submerged in concrete, so that if after removing
the casing the concrete level will go down below pile cut-of elevation, additional concrete will be poured, as needed, thru
the tremie pipes still in place. The “dirty” concrete will eventually be chipped off, in preparation for pile
cap.. |
|||||||||||||||||
|
|||||||||||||||||
|
|||||||||||||||||